Bank of America Stadium’s seating bowl and soccer-configured field on July 31, 2025; archival venue photograph before the announced full transformation.
Archival venue photograph, July31,2025: Bank of America Stadium’s seating bowl and soccer-configured field. This is not a current construction-progress image or a rendering of the renovation.Photo: Quintin Soloviev / credited source · CC BY 4.0. Source creator’s color-corrected photograph.

The North Carolina state auditor’s October 28 informational report lists Charlotte’s Bank of America Stadium-project spending through August 2026. It is an opening oversight baseline, not a completed audit.

Its tables show $2,528,684 in construction payments and $632,656 in financing expenses. Adding those subtotals produces $3,161,340. The construction total already deducts $231,444 of retained amounts.

Fully Guaranteed original logoFULLY GUARANTEED
with J. Lalwani
Follow the payment, not the ceiling.
August 2026 snapshot: retainage is deducted once; financing costs are separate.
$2,760,128Construction categoriesGross sum before retainage.
- $231,444Retainage withheldDeducted from that gross sum.
= $2,528,684Construction paymentsReported table subtotal.
+ $632,656Financing expensesSeparate reported table subtotal.
= $3,161,340Combined disbursementsOur sum of both subtotals.
Source: NC State Auditor PER-2026-7041, PDF pages5-6, released October28,2026. Snapshot through August2026; exact subtotal reconciliation by Fully Guaranteed. Public authorization: up to $650M; not fully disbursed.

A payment ledger has a specific job

Those are different measures from an authorization, a project budget or a completion estimate. Adding the retained amount back into money paid would overstate the cash that left the account. Treating early disbursements as a percentage of construction completed would answer a question that the payment ledger alone cannot settle. A project can incur financing costs before producing a finished piece of stadium.

Authorization comes before disbursement

The public commitment has its own history. Charlotte’s June 24, 2024 approved council action authorized agreements and a budget appropriation of up to $650 million for stadium improvements and a new Field House. Its terms said city-funded improvements would be owned by the city and leased to Tepper Sports & Entertainment. City payments to contractors were to follow completed work. That historical authorization is not a receipt showing the entire amount has been spent.

The North Carolina Treasurer’s April 2, 2026 announcement separately recorded Local Government Commission approval of the $650 million stadium financing request. It identified occupancy and prepared-food tax revenue as the source for debt service. Borrowing approval, borrowed principal, payments to contractors and future debt service belong in separate columns. Combining them into one spending total would count different financial events as though they were the same transaction.

An overview is not an audit verdict

The new report does not determine whether all expenditure requirements were met, intended benefits achieved or controls effective. Those questions belong to subsequent oversight.

For the city, the useful next comparison is whether each draw buys eligible work at the agreed price and whether the resulting facilities deliver what the public bargain promised. For the operator, a clear payment record can explain which obligations have been performed and which remain. That is a way to test accountability, not a claim that either side has already passed or failed the test.

What the withheld amount means

Retainage illustrates why the distinctions matter to the people doing the work. A withheld amount is different from cash received. It should not be portrayed as a contractor penalty, a forgiven obligation or a permanent saving without the terms that explain its treatment. Contractors need a reliable route from completed work to payment; the public needs a reliable route from payment to verifiable work. The ledger is where those interests meet.

Tax-funded spending also requires a broader question than whether a renovated venue will look better. A restricted revenue source still represents a public resource. The case for the project has to be assessed against the uses allowed for that money, the obligations taken on and the benefits actually delivered. A disbursement table is necessary evidence for that assessment, but it cannot finish the assessment on its own.

The Fully Guaranteed verdict

Fully Guaranteed’s view: begin with the dollars that can be reconciled, then demand evidence for the promises they are meant to buy. This opening record makes that comparison possible. It supplies neither a clean bill of financial health nor a finding of wrongdoing. Calling it a finished audit would get ahead of the very oversight the public is waiting to see.